Revision as of 06:50, 25 February 2026 by BabiSender (talk | contribs) (Created page with "= 8D-OP-01: Eight Discipline (8D) Problem Solving Procedure = ''Revised for Clarity'' '''Document Control:''' 8D-OP-01 | Rev. 0 | Effective: 30-Oct-2017 | Prepared by: IMS | Approved by: Top Management [https://next.comfaccorp.com/s/MgENbcMPSZxmgRe CGG 8D Form Download] == 1. Objective == Establish a systematic, team-based approach for identifying, analyzing, correcting, and preventing problems or nonconformities in products, services, and processes. == 2. Scope ==...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)

8D-OP-01: Eight Discipline (8D) Problem Solving Procedure

Revised for Clarity

Document Control: 8D-OP-01 | Rev. 0 | Effective: 30-Oct-2017 | Prepared by: IMS | Approved by: Top Management

CGG 8D Form Download

1. Objective

Establish a systematic, team-based approach for identifying, analyzing, correcting, and preventing problems or nonconformities in products, services, and processes.

2. Scope

Applies to all forms of nonconformity and complaints involving:

  • Products and Services
  • Fit-out category issues
  • Installation work
  • Customer Complaints
  • Internal Complaints
  • Audit findings (External and Internal)
  • Any unmet target, objective, or procedural lapse

Note: Customer-requested changes to conforming products/services are not considered nonconformities.

3. Definitions

  • Nonconformity: Deviation from agreed specifications or standards.
  • Recurrence: Repetition of a problem due to misidentification of the root cause.
  • PNC: Product Nonconformity
  • IC: Internal Complaint
  • CC: Customer Complaint
  • Executive Summary: Summary of actions and results achieved through problem-solving.
  • Discretion: IMS Team and Top Management determine if a problem warrants an 8D, based on impact and complexity.

4. References

  • Process Control Charts
  • Production Work Instructions
  • CNCP-F01: Delivery Nonconformance Report
  • CNCP-F02: Customer Complaint / Product Nonconformity Report
  • CNCP-F03: Complaints / Nonconformity Action Log
  • CA-OP-01: Corrective Action Procedure
  • CF-OP-01: Handling Customer Complaints

5. Responsibilities

Role Responsibility
Top Management / Directors Monitor complaint resolution and intervene if closure is delayed.
All Departments May raise issues using the 8D form or monitoring sheet.
Department Head / Supervisor Default Team Leader.
Department Manager Default Team Champion.
IMS Team Assigns 8D teams, ensures process compliance, and maintains monitoring.
8D Team Performs analysis, implements corrective/preventive actions, and reports results.
Management Representative (MR) Reviews and approves the final report.

6. Procedure

6.1 Completing the 8D Form

Discipline Description
D0 – Problem Awareness & Preparation Identify issue, assign CAPA number, define ownership, and document references (e.g., SO, JO, ARF, NCR, CC, IC). Include details such as area, quantity, date/time, and short description.
D1 – Problem Description Describe the issue using 5W+2H (What, When, Where, Who, Why, How Many, How Much). Attach visuals (photos, flowcharts).
D2 – Team Formation MR designates a cross-functional team to gather and analyze data.
D3 – Containment Actions Define immediate steps to control impact and prevent escalation.
D4 – Root Cause Analysis Identify Problem Cause (why it occurred) and Escape Cause (why it wasn't detected).
D5 – Corrective Actions Define and verify short-term corrective actions.
D6 – Implementation & Validation Execute and validate actions using measurable data (e.g., reduced defects, increased yield, zero recurrence).
D7 – Preventive Actions Update processes, FMEA, risk analysis, or parameters to prevent recurrence.
D8 – Closure & Recognition Summarize findings and results. Submit to Top Management for review and recognition of team efforts.

6.2 General Procedures

A. Customer Complaint Handling

  • Applies to post-handover issues not covered in punch lists.
  • Reporter completes D0 and D1, then submits to IMS.
  • IMS assigns a team and sends the file for completion.
  • Team has 1 week to complete the 8D report, including corrective and preventive actions.
  • Unresolved reports after 1 week may be subject to disciplinary review (with due process).

B. Internal Complaints (within CSC)

  • 8D Required: For major incidents (e.g., line stoppage, reworks, repeated PNCs, or issues requiring >0.5 man-day effort).
  • No 8D Needed: Minor issues logged in the complaint master list; still require root cause and corrective actions.

C. Performance Review

  • IMS issues a Monthly 8D Performance Report to Top Management summarizing open, closed, and overdue actions.

7. Documentation

  1. Completed 8D Reports (with attachments) must be archived by SSD for 3 years.
  2. Document Numbering Format:
    YY-MM-CSC-[Code]-####
    • Year (e.g., 17 → 2017)
    • Month (e.g., 09 → September)
    • CSC Site (P: Plant, M: Makati, C: Calbayog)
    • Type (CC: Customer Complaint, IC: Internal Complaint, etc.)
    • Series (0001…)

8. Clarity Improvements

  • Simplified and unified terminology (removed redundancy and old phrasing).
  • Clarified responsibility roles (Champion vs. Leader distinction).
  • Added structured tables for readability.
  • Aligned formatting for consistency with current Comfac-iT QMS style.
  • Updated example numbering format for clarity.