1. Objective
Establish a systematic, team-based approach for identifying, analyzing, correcting, and preventing problems or nonconformities in products, services, and processes.
2. Scope
Applies to all forms of nonconformity and complaints involving:
- Products and Services
- Fit-out category issues
- Installation work
- Customer Complaints
- Internal Complaints
- Audit findings (External and Internal)
- Any unmet target, objective, or procedural lapse
Note: Customer-requested changes to conforming products/services are not considered nonconformities.
3. Definitions
- Nonconformity: Deviation from agreed specifications or standards.
- Recurrence: Repetition of a problem due to misidentification of the root cause.
- PNC: Product Nonconformity
- IC: Internal Complaint
- CC: Customer Complaint
- Executive Summary: Summary of actions and results achieved through problem-solving.
- Discretion: IMS Team and Top Management determine if a problem warrants an 8D, based on impact and complexity.
4. References
- Process Control Charts
- Production Work Instructions
- CNCP-F01: Delivery Nonconformance Report
- CNCP-F02: Customer Complaint / Product Nonconformity Report
- CNCP-F03: Complaints / Nonconformity Action Log
- CA-OP-01: Corrective Action Procedure
- CF-OP-01: Handling Customer Complaints
5. Responsibilities
| Role | Responsibility |
|---|---|
| Top Management / Directors | Monitor complaint resolution and intervene if closure is delayed. |
| All Departments | May raise issues using the 8D form or monitoring sheet. |
| Department Head / Supervisor | Default Team Leader. |
| Department Manager | Default Team Champion. |
| IMS Team | Assigns 8D teams, ensures process compliance, and maintains monitoring. |
| 8D Team | Performs analysis, implements corrective/preventive actions, and reports results. |
| Management Representative (MR) | Reviews and approves the final report. |
6. Procedure
6.1 Completing the 8D Form
| Discipline | Description |
|---|---|
| D0 – Problem Awareness & Preparation | Identify issue, assign CAPA number, define ownership, and document references (e.g., SO, JO, ARF, NCR, CC, IC). Include details such as area, quantity, date/time, and short description. |
| D1 – Problem Description | Describe the issue using 5W+2H (What, When, Where, Who, Why, How Many, How Much). Attach visuals (photos, flowcharts). |
| D2 – Team Formation | MR designates a cross-functional team to gather and analyze data. |
| D3 – Containment Actions | Define immediate steps to control impact and prevent escalation. |
| D4 – Root Cause Analysis | Identify Problem Cause (why it occurred) and Escape Cause (why it wasn't detected). |
| D5 – Corrective Actions | Define and verify short-term corrective actions. |
| D6 – Implementation & Validation | Execute and validate actions using measurable data (e.g., reduced defects, increased yield, zero recurrence). |
| D7 – Preventive Actions | Update processes, FMEA, risk analysis, or parameters to prevent recurrence. |
| D8 – Closure & Recognition | Summarize findings and results. Submit to Top Management for review and recognition of team efforts. |
6.2 General Procedures
A. Customer Complaint Handling
- Applies to post-handover issues not covered in punch lists.
- Reporter completes D0 and D1, then submits to IMS.
- IMS assigns a team and sends the file for completion.
- Team has 1 week to complete the 8D report, including corrective and preventive actions.
- Unresolved reports after 1 week may be subject to disciplinary review (with due process).
B. Internal Complaints (within CSC)
- 8D Required: For major incidents (e.g., line stoppage, reworks, repeated PNCs, or issues requiring >0.5 man-day effort).
- No 8D Needed: Minor issues logged in the complaint master list; still require root cause and corrective actions.
C. Performance Review
- IMS issues a Monthly 8D Performance Report to Top Management summarizing open, closed, and overdue actions.
7. Documentation
- Completed 8D Reports (with attachments) must be archived by SSD for 3 years.
- Document Numbering Format:
YY-MM-CSC-[Code]-####
- Year (e.g., 17 → 2017)
- Month (e.g., 09 → September)
- CSC Site (P: Plant, M: Makati, C: Calbayog)
- Type (CC: Customer Complaint, IC: Internal Complaint, etc.)
- Series (0001…)
8. Clarity Improvements
- Simplified and unified terminology (removed redundancy and old phrasing).
- Clarified responsibility roles (Champion vs. Leader distinction).
- Added structured tables for readability.
- Aligned formatting for consistency with current Comfac-iT QMS style.
- Updated example numbering format for clarity.